Water collecting and supply channels system for "Vlasina" power plant | |
Channels total length | 55.300 m |
Effective cross-section | 0,50-2,70 m2 |
Channel lining | concrete |
Construction time | 1949-1957 |
Employer | Hydropower plant "Vlasina" Surdulica |
Land reclamation system - "Južnopećki kanal" | |
Channels total length | 55.300 m |
Effective cross-section | 0,50-2,70 m2 |
Channel lining | concrete |
Construction time | 1949-1957 |
Employer | Hydropower plant "Vlasina" Surdulica |
Water supply pipeline - "Lab" | |
Total pipeline length | 12.500 m |
Pressure pipeline length | 1.000 m |
Concrete pipeline diameter | 700 mm |
Pressure pipeline diameter | 500 mm |
Year of completion | 1962 |
Employer | Kosovo lignite mines "Obilić" |
Water supply pipeline for Thermo-power plant "Kosovo" III | |
Total pipeline length | 11.570 m |
Pipeline diameter | 900 mm |
Year of completion | 1966 |
Employer | Kosovo lignite mines "Obilić" |
Land reclamation system "Čitluk" Kruševac | |
Length | 20.000 m |
Cross-section | 0.10 - 1.00 m2 |
Channel lining | concrete |
Length | 22.000 m |
Diameter | 300-700 mm |
Year of completion | 1958 |
Employer | Water Community Kruševac |
Land reclamation system "Ribnik" Kruševac | |
Length | 22.000 m |
Diameter | 300-800 mm |
Year of completion | 1958 |
Employer | Water Community Kruševac |
Land reclamation system "Zabreške bare" Obrenovac | |
Construction time | 1990-1991 |
Employer | Hydropower plant "Djerdap" |
Land reclamation system "Dubravička kaseta" | |
Construction time | 1988-1989 |
Employer | Hydropower plant "Djerdap" |
Drainage channel "Borča 2" | |
Year of completion | 1998 |
Employer | Hydropower plant "Djerdap" |
Drainage system "Velika bara" Kupinac-Obrenovac | |
Drainage area | 8.600 ha |
Construction time | 1985-1986 |
Employer | Agricultural combine "Beograd" |
Fish pond in Dokmir village, Ub | |
Construction time | 1989 |
Employer | AIK"Valjevo" PIK UB |
Drainage system "Vukićevica" with pump station, Obrenovac | |
Drainage system area | 4.500 ha |
Construction time | 1989 |
Employer | PKB "Dragan Marković" |
Pump stations (5 units) | |
Average dimensions of station | 5x15x6 m |
Construction time | 1984-1986 |
Employer | Hydropower plant "Djerdap" Beograd |
Development of Velika Morava river upper part | |
Length of development area | 11.600 m |
Year of completion | 1963 |
Employer | Directorate for development of Velika Morava catchment area |
Nišava river development project | |
Length of development area | 9.500 m |
Year of completion | 1958 |
Employer | Water development directorate ,Beograd |
Trbusnica river development project | |
Length of development area | 6.500 m |
Year of completion | 1957 |
Employer | Factory "Viskoza" Loznica |
Toplodoiska river development project | |
Length of development area | 1.400 m |
Construction time | 1986-1987 |
Employer | Water utilization company of Beograd |
"Resnik" dam and storage reservoir | |
Year of completion | 1987 |
Employer | Water utilization company of Beograd |